Operation Sequence of Commercial Peanut Butter Making Machine
Category: Blog
The correct operation sequence of commercial peanut butter making machine is as fellows:
1. Turn on the cooling water. Cooling water pressure is about 0.15Mpa, the water temperature is not higher than 25 deg. The cooling water can be recycled after filtration.
1. Turn on the cooling water. Cooling water pressure is about 0.15Mpa, the water temperature is not higher than 25 deg. The cooling water can be recycled after filtration.
2. Turn on the motor.
Note: no material or other solvents are put into use until the equipment is running properly.
3. Adjust the machining gap of stator and rotor.
1) turn the two fixed lever in counter clockwise direction.
2) adjust the rotation of the adjusting ring by moving the fixed lever, and adjust the clearance between the rotor and the stator. The adjusting ring rotates clockwise, the clearance between the stator and the rotor becomes smaller, the material granularity becomes thinner; the adjusting ring rotates counterclockwise, the clearance between the stator and rotor becomes larger, and the particle size of the material becomes coarse.
3) according to the fineness and yield requirement of processing material, the optimum clearance between stator and rotor is selected.
Note: 0 units have been set up when the equipment is out of the factory.
The clearance of the stator and rotor shall be determined by testing according to the properties and fineness requirements of the material to be processed.
The clearance adjustment shall be carried out in the running state of the machine.
4) turn the two fixed rod clockwise.
Note: according to the batch production situation, the limit screw can be used to limit the rotation of the adjusting ring so as to achieve the purpose of limiting the clearance between the stator and the rotor.
According to the use of the materials should be regularly tested fineness, timely adjustment of stator and rotor gap.
After replacing the stator and rotor, the 0 bit shall be reset and the clearance should be adjusted.
4. Adding materials for processing.
Note: The equipment can not process dry solid materials, only wet processing.
The feed size shall be less than 1mm. Materials should be removed before entering the equipment. No iron or crushed stone particles are allowed to enter the equipment so as to prevent damage to the machine.
According to the material properties and processing fineness requirements, can be done once or more grinding.